Library Refurbishment: works over next two weeks

We’re approaching the halfway point for early works now, continuing to build towards the demolition of the glass-fronted staircase. Work over the next two weeks will largely focus on finishing off the internal hoardings and continued activity around the glass-fronted staircase.

Main works proposed up to Sunday 18 September 2016:

  • Internal hoardings on the Ground, 1st, 3rd and 5th Floors should be completed, with doors added for construction workers to access work areas. It goes without saying that these areas are strictly off limits to Library users, so please keep out!
  • Work around the glass-fronted staircase will continue from the Basement all the way up to the 2nd Floor.
  • The 2nd Floor is expected to reopen for full use during the week beginning Monday 12 September (date subject to change), including the group study area.
  • Once the 2nd Floor has reopened the 4th Floor will undergo the same programme of works that were recently carried out on the 2nd floor. As a result the 4th Floor will be closed temporarily. If you were looking to use the group study area on the 4th Floor, please use the space available on the 2nd Floor instead.
  • Outside, hoarding will be set up around the bike shed area so that ground works can begin.

Additional details can be found in a floor-by-floor plan. In addition, our contractors ISG have prepared a helpful news bulletin tracking progress over the past month.

As usual, the noisiest sections of work will be carried out up until 10:00am.

Please contact Robin Hunter if you have any queries. Additional information about the Library refurbishment can be found at www.reading.ac.uk/library/refurb.