Library refurbishment works 6 – 27 March

Image of refurbished University Library surrounded by seating, trees and hedges.Between 6–27 March the following construction/internal work is expected to be carried out:

  • Re-cladding the outside: Work around the outside of the Library continues as our contractors focus on re-cladding the Library’s exterior. These works involve drilling and so may be noisy – details of alternative study space are available on the Library refurbishment project page.
  • Ground works: Ground works continue around the perimeter of the Library.
  • Internal works: Activity will resume around the glass-fronted staircase (behind the white hoardings). Later in this period furniture from the 2nd and 4th Floor group study areas will start moving into the URS Building – we’ll be sharing more details of the URS move very shortly.

For details of alternative spaces and the latest project news, please visit our Library refurbishment project page.

Rachel Redrup, Marketing Co-ordinator for University Communications