AV Upgrades

AV UPGRADES 2019/20:

Rooms completed and scheduled for the current academic year:

Location Start Finish Status
Lond Rd L22 G06 09/09/2019 20/09/2019 Completed
Lond Rd L22 G07 09/09/2019 20/09/2019 Completed
Palmer 102 19/09/2019 19/09/2019 Completed
Palmer 105 20/09/2019 27/09/2019 Completed
Edith Morley 128 30/09/2019 08/10/2019 Completed
Chemistry LTG 11/10/2019 01/11/2019 Scheduled
Hopkins 101 04/11/2019 12/11/2019 Scheduled
Miller G19 15/11/2019 26/11/2019 Scheduled
IOD 09/12/2019 10/01/2020 Scheduled
National Grid 06/01/2020 23/01/2020 Scheduled
Palmer 101 13/02/2020 21/02/2020 Scheduled
Lond Rd L33 101 24/02/2020 28/02/2020 Scheduled
WKH Committee Room 2* 30/03/2020 07/04/2020 Scheduled
Chemistry LT1 25/05/2020 12/06/2020 Scheduled

 

*New AV equipment has been installed as a temporary measure to overcome issues with failing equipment.  The installation work will be completed as scheduled.